Spring naar inhoud

Information about the tariff structure of Gasunie Deutschland Transport Services GmbH as of 01.01.2024 being valid at cross-border points and storages

Gasunie Deutschland Transport Services GmbH (GUD) publishes the capacity charge for grid access in calendar year 2024, which is valid at cross-border points and storages (capacity charge).

The capacity charge for firm flexible allocable entry and exit capacities with a duration of one year amounts to:

           5.10 [€/(kWh/h)/a]

Compared to 2023 the tariff for firm freely allocable entry and exit capacities in the THE market area will be around 15.4 percent lower.

The capacity charge for dynamically-allocable entry and exit capacities amounts to 80 percent and for conditionally firm freely allocable entry and exit capacities 90 percent of the respective applicable capacity charge for firm flexible allocable entry and exit capacities.

According to the decision BK9-22/612 (MARGIT 2024) a multiplier is to be applied at all interconnection points for the conversion from yearly standard capacity products to non-yearly standard capacity products. The multiplier of a within-day standard capacity product is 2.0, the multiplier of a daily standard capacity product is 1.4, the multiplier of a monthly standard capacity product is 1.25 and the multiplier of a quarterly standard capacity product is 1.1.

Reserve prices for standard interruptible capacity products at interconnection points shall be calculated by multiplying the reserve prices for standard firm capacity products calculated in accordance with Articles 14, 15 of Regulation (EU) No 2017/460 (NC TAR) and the decision  BK9-19/610, (REGENT 2021) with the difference between 100% and the amount of the applicable ex-ante discount at the respective interconnection point for each standard capacity product in accordance with Annex I of the decision BK9-22/612 (MARGIT 2024). - Draft

In accordance with decision BK9-22/612 (MARGIT 2024), a discount of 40% on the capacity charge for firm freely allocable capacity shall apply to LNG entry points for annual and quarterly bookings of firm freely allocable capacity.

For capacity bookings at gas storage facilities, a uniform discount of 75% on the capacity charge for firm freely allocable capacity is granted in accordance with the decision REGENT 2021 (BK9-19/610) Tenor Ziffer 2, insofar as they are not used as cross-border interconnection points.

In addition, the regulations of BEATE 2.0 (BK9-18/608) and the amendment of BEATE 2.0 (BK9-20/608) are applied to capacity bookings at storages.

In case of questions please do not hesitate to contact your contact person at Gasunie Deutschland or submit an email to us.