Information about the tariff structure of Gasunie Deutschland Transport Services GmbH as of 01.01.2022 until 31.12.2022 for the market area Trading Hub Europe being orderable network points
Gasunie Deutschland Transport Services GmbH (GUD) as TSO publishes the capacity charge for grid access for the calendar year 2022 for the market area Trading Hub Europe (“THE”), which are valid at all orderable network points.
Due to regulatory requirements (decisions “REGENT-GP” (BK9-18/611-GP) and “AMELIE”(BK9-18/607)), a postage stamp RPM is in place since 01.01.2020 and reference prices of GUD have been calculated accordingly. The regulatory requirements REGENT and AMELIE have been appealed by third parties. The Higher Court OLG Düsseldorf dismissed the appeals in 16th September 2020. The complainants have appealed to the Federal Court of Justice (BGH) against the decision of the OLG Düsseldorf. For the new german market area Trading Hub Europe (“THE”) two new decisions REGENT 2021 (BK9-19/610) and AMELIE (BK9-19/607) were enacted by the BNetzA. These decisions have been appealed by third parties, too. As a result of possible legal disputes it cannot be excluded that regulatory requirements could be changed and thus the reference prices could be increased both for the future and retroactively. This is why GUD reserves the right to amend the reserve prices on the basis of legal / regulatory decisions. In addition, GUD reserves the right to request the difference be-tween the reference price paid by the shipper and the new reference price established on the basis of a legal / regulatory decision.
The capacity charge for orderable firm flexible allocable exit capacities for the market area THE amounts to:
3.51 [€/(kWh/h)/a]
According to BEATE 2.0 (BK9-18/608) and the amendment of BEATE 2.0 (BK9-20/608) the security surcharge for calculating the discount for interruptible capacity at all network points in the H-gas transmission system is twenty (20) percent. The security surcharge for calculating the discount for interruptible capacity at all network points in the L-gas transmission system remains at (10) percent.
In case of questions please do not hesitate to contact your contact person at Gasunie Deutschland or submit an email to us.